Notice #54687
Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved Roads along Sayre Highway - (S01381MN) Chainage 097.50 - Chainage 120, Manolo Fortich, Bukidnon
Department of Public Works and Highways - Bukidnon 3rd DEO
Scope
Reconstruct concrete pavement with road markings and a double-arm solar LED roadway light.
show the full notice texthide the notice text
Republic of the Philippines DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS BUKIDNON 3 RD DISTRICT ENGINEERING OFFICE Dicklum, Manolo Fortich, Bukidnon, Region X -------------------------------------------------------------------------------------------------------------------------------------- INVITATION TO BID The Department of Public Works and Highways (DPWH) Bukidnon 3 rd DEO, Dicklum, Manolo Fortich, Bukidnon, through its Bids and Awards Committee (BAC), invites contractors to submit bids for the following contracts: 1. Contract ID No. : 26KC0107 Contract Name : Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved Roads along Sayre Highway - (S01381MN) Chainage 097.50 - Chainage 120 Location : Manolo Fortich, Bukidnon Scope of Work : Reconstruction of concrete pavement, 350mm thick PCCP, 6.7m width with pavement markings and Double Arm Solar LED Roadway Lighting, 12m Pole, 80W-125W, 1 – Unit Source of Funds : GAA 2026 Appropriation : Php 964,000.00 ABC : Php 944,720.00 Contract Duration : 28 Calendar Days Cost of Bid Documents : 1,000.00 The BAC is conducting the public bidding for this Contract in accordance with Republic Act No. 12009 (NGPA) and its Implementing Rules and Regulations (IRR). To be eligible to bid for this Contract, a contractor must meet the following major requirements: Duly licensed Filipino citizens or sole proprietorship; (b) Partnerships duly organized under the laws of the Philippines and of which at least sixty percent (60%) of the interest belongs to citizens of the Philippines; (c) Corporations duly organized under the laws of the Philippines and of which at least sixty percent (60%) of the outstanding capital stock belongs to the citizens of the Philippines; (d) For persons or entities forming themselves into a Joint Venture (JV), Filipino ownership or interest of the joint venture concerned shall be at least sixty percent (60%); (e) The bidder must have completed an SLCC that is similar to the procurement project to be bid, and whose value, adjusted to current prices using the PSA consumer price indices, must be at least 50% of the ABC to be bid; AND (f) The SLCC shall be supported by an Owner’s Certificate of Final Acceptance issued by the project owner than the contractor, or a final rating of at least satisfactory in the CPES The DPWH will use non-discretionary “pass/fail” criteria in the eligibility check, preliminary examination of bids, evaluation of bids, post-qualification, and award. The schedule of key procurement activities for this Contract is shown below: Activity Time & Date Place Issuance of Bidding Documents AUGUST 6 - 25, 2026 until 10:00 A.M. only Hard copies at BAC Secretariat, DPWH-Bukidnon 3 rd DEO, Dicklum, Manolo Fortich, Bukidnon Downloadable from DPWH & PhilGEPs websites Pre-bid Conference AUGUST 13, 2026 @ 10:30 A.M. Conference Room, DPWH-Buk 3 rd DEO Meeting ID: __________ Passcode: __________ Receipt by the BAC of Bids AUGUST 25, 2026 until 12:00 Noon only BAC, DPWH-Buk 3 rd DEO, Dicklum, Manolo Fortich, Bukidnon - Deadline of Submission of Official Receipts is on AUGUST 25, 2026 until 10:00 A.M only For Electronic submission of bids, send to: electronicbids_bukidnon3@dpwh.gov.ph Uploading of OFFICIAL RECEIPT of Bid Document up to 10:00 a.m. only Opening of Bids AUGUST 25, 2026 @ 2:00 P.M. Bidders shall pay the BAC an applicable fee indicated above per project for the Bidding Documents, upon securing hard copies of the documents. Bidders that download the documents from the DPWH/PhilGEPS website shall pay the fee upon submission of their bids. The HoPE of DPWH-Bukidnon 3 rd District Engineering Office reserves the right to reject any and all bids, declare a failure of bidding, or not award the contract, in situations that are not in accordance with the provisions of Section 70 Reservation Clause of RA 12009 (NGPA) and its IRR. In order to establish a fair and transparent system for managing offenses committed by bidders in the procurement of infrastructure, goods, and Consulting Services projects through bidding, All interested bidders are hereby informed of the strict implementation of Department Order No. 28 Series of 2024, “ Three (3) – Strike Policy in the Procurement of Infrastructure, Goods and Consulting Services Contracts”. Any requests for additional information concerning this bidding shall be directed to the following: RAMIL GIOVANNI T. KINTANAR ROBERT M. VALLES BAC Chairman Head, Secretariat DPWH, Bukidnon 3 rd DEO DPWH, Bukidnon 3 rd DEO Dicklum, Manolo Fortich, Bukidnon Dicklum, Manolo Fortich, Bukidnon Approved by: RAMIL GIOVANNI T. KINTANAR BAC Chairman DPWH, Bukidnon 3 rd DEO Dicklum, Manolo Fortich, Bukidnon Website: https://www.dpwh.gov.ph DPWH-INFRA-04-2016
Requirements
show the 10 standard requirementshide the standard requirements
confirm these in the bid documents
- PhilGEPS Certificate of Platinum Registration (Annex A eligibility documents current)IRR §8.5.2
- Registration certificate — SEC, DTI, or CDAIRR §23.1
- Valid Mayor's / business permitIRR §23.1
- Tax clearanceEO 398
- Statement of ongoing contracts + single largest completed similar contract (SLCC) ≥ 50% of the ABCIRR §23.1
- Audited financial statements, stamped received by BIRIRR §23.1
- Net Financial Contracting Capacity (NFCC) ≥ ABCIRR §23.1
- Omnibus Sworn Statement, notarizedIRR §25.3
- Bid security: 2% cash/cashier's check, 5% surety bond, or bid-securing declarationIRR §27.2
- Valid PCAB contractor's license, category matching the ABCRA 4566
Contact
Maria Teresa Fernandez
From the bid documents
checking for enriched data…